With excavation completed, a contract was signed for piling work. However, with continued
controversy, reluctance on the part of Government to authorise spending, and uncertainty about
obtaining adequate building supplies, further compromises were needed.
The piling contractor was told to stop work, and there was talk of legal action being taken by
him to recoup costs.
Eventually, agreement was reached to construct a 210-bed 3-wing, 3-storey block, on the
already excavated site.
There was already an urgent need to accommodate injured servicemen, and the Defence
Department erected a 2-storey temporary 'Soldiers' Block' directly in front of the old main
entrance.
|